Industrial Engineering and Operations Research MCQs 2026

70 questions with detailed answers · 25 from past papers · 7 quiz batches available

📚 Mechanical Engineering📄 25 Past-Paper Qs✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1Questions 1–10 of 70
  1. Q1Past Paper · PPSC/FPSC/NTSeasy

    Industrial engineering primarily focuses on

    1. Aonly chemical reaction kinetics
    2. Boptimization of integrated systems of people, materials and equipment
    3. Conly astronomical navigation
    4. Donly literary criticism
    💡 Explanation:

    IE improves productivity and efficiency of complex systems.

  2. Q2Past Paper · PPSC/FPSC/NTSeasy

    Method study in industrial engineering is concerned with

    1. Ameasuring worker blood pressure only
    2. Bexamining and improving the way a job is done
    3. Cdesigning boiler tubes only
    4. Dcalculating beam deflection only
    💡 Explanation:

    Method study eliminates wasteful motions and sequences.

  3. Q3Past Paper · PPSC/FPSC/NTSeasy

    Time study is used to determine

    1. Astandard time required to perform a job
    2. Bchemical composition of alloys
    3. Cfluid viscosity only
    4. Delectrical resistance of wire only
    💡 Explanation:

    Time study establishes norms for planning and incentives.

  4. Q4medium

    Therbligs are

    1. Atypes of welding electrodes
    2. Bboiler mountings
    3. Cbasic elemental motions in motion study
    4. Dturbine blade profiles
    💡 Explanation:

    Gilbreth classified fundamental motions like reach, grasp and transport.

  5. Q5easy

    A flow process chart records

    1. Aonly financial ledger entries
    2. Bonly gear tooth profiles
    3. Conly steam pressure readings
    4. Dsequence of operations and inspections in a process
    💡 Explanation:

    Flow charts visualize material and information flow.

  6. Q6medium

    String diagram is used in plant layout to show

    1. Astress distribution in a beam
    2. Bmagnetic field lines only
    3. Cphase diagram of steel only
    4. Dmovement of materials or workers on a scale plan
    💡 Explanation:

    String diagrams quantify travel distance for layout improvement.

  7. Q7medium

    Travel chart in layout study plots

    1. Acompressor polytropic exponent only
    2. Bhardness versus tempering time only
    3. Cfrequency of movement between departments
    4. Dvoltage versus current only
    💡 Explanation:

    From-to charts guide rearrangement to reduce handling.

  8. Q8Past Paper · PPSC/FPSC/NTSeasy

    Line balancing aims to

    1. Abalance chemical equations only
    2. Bequalize boiler drum levels only
    3. Cdistribute work evenly among stations on an assembly line
    4. Dmatch turbine inlet temperature only
    💡 Explanation:

    Balancing minimizes idle time and maximizes line output.

  9. Q9Past Paper · PPSC/FPSC/NTSmedium

    Cycle time on an assembly line is determined by

    1. Athe slowest workstation (bottleneck)
    2. Bthe fastest worker always
    3. Caverage of all breaks only
    4. Dtotal plant electricity demand
    💡 Explanation:

    Line output rate equals bottleneck station rate.

  10. Q10medium

    Number of workstations for a given cycle time equals

    1. Asum of all wages
    2. Bproduct weight only
    3. Cnumber of supervisors
    4. Dtotal work content divided by cycle time (rounded up)
    💡 Explanation:

    Required stations = ⌈Σ task times / cycle time⌉.

  11. Q11Past Paper · PPSC/FPSC/NTSeasy

    Economic Order Quantity (EOQ) minimizes

    1. Atotal ordering and holding costs
    2. Bonly transportation fuel cost
    3. Conly labour overtime only
    4. Donly machine depreciation only
    💡 Explanation:

    EOQ balances setup cost against inventory carrying cost.

  12. Q12medium

    In EOQ model, annual holding cost increases with

    1. Aorder quantity
    2. Border frequency only
    3. Csetup cost only
    4. Dunit purchase price only if unrelated to stock level
    💡 Explanation:

    Larger batches raise average inventory and holding cost.

  13. Q13Past Paper · PPSC/FPSC/NTSmedium

    Reorder point depends on

    1. Acolour of packaging only
    2. BCEO tenure only
    3. Cdemand during lead time and safety stock
    4. Dmachine paint scheme only
    💡 Explanation:

    ROP = demand rate × lead time + safety stock.

  14. Q14easy

    ABC analysis classifies inventory by

    1. Aalphabetical product names only
    2. Bphysical weight only
    3. Cannual consumption value
    4. Dsupplier country only
    💡 Explanation:

    A items are few but high value; C items are many low value.

  15. Q15Past Paper · PPSC/FPSC/NTSeasy

    PERT is used mainly for

    1. Aproject scheduling with uncertain activity times
    2. Bmetal cutting speed only
    3. Cgear train design only
    4. Drefrigerant selection only
    💡 Explanation:

    Program Evaluation and Review Technique handles probabilistic durations.

  16. Q16Past Paper · PPSC/FPSC/NTSeasy

    CPM assumes activity durations are

    1. Adeterministic (known)
    2. Balways zero
    3. Crandom with beta distribution only
    4. Dequal to project float always
    💡 Explanation:

    Critical Path Method uses fixed times for network analysis.

  17. Q17Past Paper · PPSC/FPSC/NTSmedium

    Critical path in a project network is

    1. Athe path with most resources visually
    2. Bany path with zero cost
    3. Cthe shortest path always
    4. Dthe longest path determining minimum project duration
    💡 Explanation:

    Delay on critical path delays entire project.

  18. Q18medium

    Float (slack) of a non-critical activity is

    1. Aalways negative
    2. Btime it can be delayed without delaying project
    3. Cequal to project duration
    4. Dsame as setup time always
    💡 Explanation:

    Slack = LS − ES = LF − EF.

  19. Q19medium

    Dummy activity in CPM network represents

    1. Aactual welding operation
    2. Blogical dependency without consuming time or resources
    3. Cmaterial storage only physically
    4. Dworker lunch break time
    💡 Explanation:

    Dummies preserve precedence relationships.

  20. Q20hard

    Crashing a project means

    1. Areducing duration by adding resources at higher cost
    2. Bcanceling all inspections
    3. Cremoving the critical path
    4. Ddecreasing quality always
    💡 Explanation:

    Crash cost trade-off seeks minimum cost for target duration.

  21. Q21Past Paper · PPSC/FPSC/NTSeasy

    Linear programming seeks to

    1. Aoptimize a linear objective subject to linear constraints
    2. Bsolve only quadratic equations
    3. Cmeasure surface roughness only
    4. Ddesign cam profiles only
    💡 Explanation:

    LP maximizes or minimizes Z = c₁x₁ + c₂x₂ + … under restrictions.

  22. Q22medium

    Feasible region in LP is

    1. Aonly the origin point
    2. Bobjective function line only
    3. Cunbounded profit always
    4. Dset of points satisfying all constraints
    💡 Explanation:

    Corner point theorem: optimum occurs at feasible corner.

  23. Q23hard

    Simplex method solves LP by

    1. Arandom search only
    2. Bintegration of curves only
    3. Cmoving from vertex to vertex improving objective
    4. Dfinite element meshing only
    💡 Explanation:

    Simplex iterates on basic feasible solutions.

  24. Q24Past Paper · PPSC/FPSC/NTSmedium

    In a single-server queuing system, arrival rate λ and service rate μ must satisfy for stability

    1. Aλ > μ always
    2. Bλ = μ always
    3. Cμ = 0
    4. Dλ < μ
    💡 Explanation:

    Traffic intensity ρ = λ/μ must be less than 1.

  25. Q25medium

    Average waiting time in queues generally increases when

    1. Aarrival rate drops to zero
    2. Bservice rate exceeds arrival rate greatly
    3. Cqueue discipline is ignored
    4. Dutilization of server approaches 100%
    💡 Explanation:

    Heavy traffic causes long waits nonlinearly.

  26. Q26hard

    Little's Law states L =

    1. Aλ / W only
    2. Bλ W (average number in system = arrival rate × average time in system)
    3. Cλ + W
    4. Dμ − λ
    💡 Explanation:

    Fundamental queuing relation L = λW.

  27. Q27medium

    Work sampling is used to

    1. Ameasure exact cutting force continuously
    2. Bchemical analysis of slag
    3. Cestimate proportion of time spent on activities by random observations
    4. Dultrasonic thickness only
    💡 Explanation:

    Statistical sampling determines activity percentages.

  28. Q28easy

    Allowance in time study accounts for

    1. Aprofit margin only
    2. Bpersonal, fatigue and delay factors
    3. Cmaterial cost only
    4. Dtool rake angle only
    💡 Explanation:

    Normal time is increased by allowance percentage.

  29. Q29medium

    Performance rating in time study compares

    1. Aobserved worker pace to standard pace
    2. Bmachine colour to standard
    3. Cmaterial density to standard only
    4. Droom temperature to standard only
    💡 Explanation:

    Analyst rates speed and effort versus defined normal.

  30. Q30Past Paper · PPSC/FPSC/NTSmedium

    Standard time equals

    1. Aobserved time only without rating
    2. Bbreak time squared
    3. Cnormal time × (1 + allowance fraction)
    4. Dsetup time minus run time
    💡 Explanation:

    ST = NT(1 + A) includes justified delays.

  31. Q31Past Paper · PPSC/FPSC/NTSeasy

    Value engineering aims to

    1. Aincrease gold plating on all parts
    2. Bprovide necessary function at lowest life-cycle cost
    3. Cmaximize weight always
    4. Deliminate all testing
    💡 Explanation:

    VE analyzes function versus cost systematically.

  32. Q32easy

    Forecasting methods include

    1. Aonly Rockwell hardness test
    2. Bonly Charpy impact only
    3. Conly Brinell test only
    4. Dmoving average and exponential smoothing
    💡 Explanation:

    Quantitative forecasting uses historical demand patterns.

  33. Q33medium

    Exponential smoothing gives more weight to

    1. Aoldest data only
    2. Bonly outliers
    3. Czero weight to all data
    4. Drecent observations
    💡 Explanation:

    Smoothing constant α controls recency emphasis.

  34. Q34Past Paper · PPSC/FPSC/NTSmedium

    Master production schedule drives

    1. Aonly cafeteria menu
    2. Bonly parking allocation
    3. Cdetailed production and procurement plans
    4. Donly annual audit report
    💡 Explanation:

    MPS states what to build and when at finished-item level.

  35. Q35easy

    Bill of materials (BOM) lists

    1. Aemployee salaries only
    2. Bcomponents and quantities to make a product
    3. Cboiler safety valve settings only
    4. Dturbine blade angles only
    💡 Explanation:

    BOM structures material requirements for MRP.

  36. Q36medium

    MRP logic explodes BOM based on

    1. Aweather forecast only
    2. Bstock market index
    3. Ccolour preferences only
    4. Dmaster schedule and inventory records
    💡 Explanation:

    Material Requirements Planning nets demand against stock.

  37. Q37Past Paper · PPSC/FPSC/NTSeasy

    Kanban is associated with

    1. Apull production and visual inventory control
    2. Bpush system with large batches only
    3. Cbatch-and-queue mass inventory always
    4. Dproject crashing only
    💡 Explanation:

    Cards signal replenishment in JIT systems.

  38. Q38Past Paper · PPSC/FPSC/NTSeasy

    Just-in-Time (JIT) seeks to

    1. Amaximize warehouse stock always
    2. Bminimize inventory by producing only what is needed when needed
    3. Cincrease setup times
    4. Dignore supplier quality
    💡 Explanation:

    JIT reduces waste and lead time.

  39. Q39medium

    5S workplace organization includes Seiri, Seiton, Seiso, Seiketsu and

    1. AShitsuke (sustain discipline)
    2. BShinkansen
    3. CShogun
    4. DShimano
    💡 Explanation:

    Fifth S sustains the other four practices.

  40. Q40easy

    Bottleneck resource in production limits

    1. Aoffice stationery supply only
    2. Blogo design only
    3. Cthroughput of the entire system
    4. Dparking slots only
    💡 Explanation:

    Theory of Constraints focuses on system constraint.

  41. Q41medium

    Theory of Constraints five focusing steps begin with

    1. Ahire more marketing staff
    2. Bidentify the system constraint
    3. Cpaint machines green
    4. Dincrease batch size blindly
    💡 Explanation:

    First find what limits throughput.

  42. Q42easy

    Product layout is best for

    1. Aunique one-off shipbuilding only
    2. Bhigh-volume standardized products
    3. Chospital surgery scheduling only
    4. Dresearch library catalog only
    💡 Explanation:

    Assembly lines use product-oriented arrangement.

  43. Q43easy

    Process layout groups

    1. Aproducts in fixed sequence lines only
    2. Bonly executive offices
    3. Conly finished goods pallets in line
    4. Dsimilar machines or functions together
    💡 Explanation:

    Job-shop layout handles varied routes and low volume.

  44. Q44medium

    Fixed-position layout is used for

    1. Alarge bulky products like ships and aircraft
    2. Bpen manufacturing only
    3. Csoft drink bottling only
    4. Dpaper clip assembly only
    💡 Explanation:

    Product stays put; resources come to it.

  45. Q45Past Paper · PPSC/FPSC/NTSeasy

    Ergonomics in IE addresses

    1. Amaximizing noise exposure
    2. Beliminating all breaks
    3. Cfitting the job to the worker to reduce fatigue and injury
    4. Dignoring posture always
    💡 Explanation:

    Human factors design improves safety and performance.

  46. Q46medium

    Learning curve effect means

    1. Aquality always decreases
    2. Btime per unit decreases as cumulative production increases
    3. Ccost per unit rises always
    4. Dworkers forget skills
    💡 Explanation:

    Experience curve reflects improving proficiency.

  47. Q47Past Paper · PPSC/FPSC/NTSeasy

    Break-even analysis finds quantity where

    1. Amarginal cost is zero only
    2. Bprofit is maximized always
    3. Cfixed cost is zero
    4. Dtotal revenue equals total cost
    💡 Explanation:

    BEP: F + vQ = pQ.

  48. Q48easy

    Fixed cost in break-even context

    1. Achanges with every unit always
    2. Bequals variable cost always
    3. Cis always zero
    4. Ddoes not vary with production volume in short run
    💡 Explanation:

    Rent and salaries often treated as fixed.

  49. Q49Past Paper · PPSC/FPSC/NTSeasy

    Productivity ratio can be expressed as

    1. Ainput divided by output only for IE
    2. Bprofit divided by tax only
    3. Cweight divided by colour
    4. Doutput divided by input
    💡 Explanation:

    Productivity measures efficiency of resource use.

  50. Q50Past Paper · PPSC/FPSC/NTSmedium

    Overall Equipment Effectiveness (OEE) combines

    1. Aonly machine colour metrics
    2. Bavailability, performance and quality
    3. Conly office attendance
    4. Donly shipping distance
    💡 Explanation:

    OEE = A × P × Q for equipment utilization.

  51. Q51easy

    Depreciation in engineering economy represents

    1. Adaily wage payments
    2. Ballocation of capital asset cost over useful life
    3. Craw material spoilage only
    4. Dincome tax refund
    💡 Explanation:

    Accounting charge for asset consumption.

  52. Q52Past Paper · PPSC/FPSC/NTSmedium

    Present worth analysis discounts

    1. Aonly physical dimensions
    2. Bfuture cash flows to a common time using interest rate
    3. Conly hardness values
    4. Donly temperature readings
    💡 Explanation:

    Time value of money guides investment decisions.

  53. Q53hard

    Internal rate of return (IRR) is the discount rate that makes

    1. Apayback period zero always
    2. Bprofit infinite
    3. Cnet present value equal to zero
    4. Ddepreciation zero
    💡 Explanation:

    IRR compares project yield to hurdle rate.

  54. Q54easy

    Payback period measures

    1. Atime to recover initial investment from cash flows
    2. Bproduct colour fading time
    3. Ctool rake angle
    4. Dworker height only
    💡 Explanation:

    Simple metric ignoring time value after payback.

  55. Q55Past Paper · PPSC/FPSC/NTSmedium

    Sunk cost should generally be

    1. Adoubled in calculations
    2. Bthe only cost considered
    3. Cignored in future decision making
    4. Dadded to opportunity cost twice
    💡 Explanation:

    Irrecoverable past costs are irrelevant to forward choices.

  56. Q56medium

    Opportunity cost in IE decisions is

    1. Aaccounting depreciation only
    2. Bscrap metal price only always
    3. Cvalue of the best forgone alternative
    4. Dsunk labour from last year
    💡 Explanation:

    True economic cost includes alternatives sacrificed.

  57. Q57hard

    Monte Carlo simulation in OR uses

    1. Arandom sampling to model uncertainty
    2. Bonly deterministic LP
    3. Conly hand sketching
    4. Donly one scenario always
    💡 Explanation:

    Repeated trials estimate risk in project outcomes.

  58. Q58medium

    Transportation model in LP minimizes

    1. Aworker fatigue only
    2. Bnoise level only
    3. Csurface roughness only
    4. Dcost of shipping from sources to destinations
    💡 Explanation:

    Balanced transport table optimizes distribution.

  59. Q59hard

    Assignment problem is special case where

    1. Aunlimited shipments allowed always
    2. Beach source assigned to one destination one-to-one
    3. Cno costs exist
    4. Ddemand is infinite
    💡 Explanation:

    Hungarian method solves personnel-machine matching.

  60. Q60medium

    Simulation differs from optimization because it

    1. Aalways finds global optimum analytically
    2. Bignores randomness always
    3. Cdescribes system behaviour under scenarios without guaranteeing optimum
    4. Duses only calculus
    💡 Explanation:

    Simulation models complex stochastic systems.

  61. Q61easy

    Gantt chart displays

    1. Aactivities as bars on a time scale
    2. Bstress-strain curve only
    3. CMollier diagram only
    4. DSankey of enthalpy only
    💡 Explanation:

    Visual schedule for progress monitoring.

  62. Q62easy

    Milestone on a project chart marks

    1. Aevery coffee break
    2. Brandom paint colour
    3. Csignificant event or completion of a major deliverable
    4. Ddaily humidity reading
    💡 Explanation:

    Key checkpoints without duration themselves.

  63. Q63medium

    Cellular manufacturing groups

    1. Aall lathes in one building only always
    2. Bdissimilar machines into product-focused cells
    3. Conly office staff
    4. Donly quality auditors
    💡 Explanation:

    Group technology reduces material travel.

  64. Q64Past Paper · PPSC/FPSC/NTSmedium

    Takt time is calculated as

    1. Atotal employees times wage rate
    2. Bmachine weight divided by power
    3. Cfloor area only
    4. Davailable production time divided by customer demand rate
    💡 Explanation:

    Takt sets pace to match market pull.

  65. Q65medium

    Andon system provides

    1. Aencrypted email only
    2. Bvisual signal for abnormal conditions on production line
    3. Cannual financial audit only
    4. Dblueprint filing only
    💡 Explanation:

    Lights/boards alert teams to stop and fix problems.

  66. Q66Past Paper · PPSC/FPSC/NTSmedium

    Poka-yoke means

    1. Amistake-proofing a process or product design
    2. Bincreasing defect rate
    3. Chiding errors from inspectors
    4. Dmaximizing rework
    💡 Explanation:

    Error-proof devices prevent wrong assembly.

  67. Q67medium

    Six Sigma targets defect rate near

    1. A3.4 defects per million opportunities
    2. B50 percent defects
    3. C100 percent rework
    4. Dzero measurement
    💡 Explanation:

    DMAIC reduces process variation statistically.

  68. Q68easy

    DMAIC stands for Define, Measure, Analyze, Improve and

    1. ACancel
    2. BCopy
    3. CCompile
    4. DControl
    💡 Explanation:

    Control phase sustains gains with monitoring.

  69. Q69easy

    Lean manufacturing primarily eliminates

    1. Aall inventory regardless of need blindly
    2. Ball automation
    3. Cwaste (muda) in processes
    4. Dall standards
    💡 Explanation:

    Lean focuses on value-adding activities only.

  70. Q70medium

    SMED aims to reduce

    1. Achangeover/setup time
    2. Bproduct quality always negatively
    3. Cemployee training to zero
    4. Dcustomer orders
    💡 Explanation:

    Single-minute exchange of die enables small batches.