Project Planning and Quantity Surveying MCQs 2026
50 questions with detailed answers · 21 from past papers · 5 quiz batches available
Choose a Quiz Batch. Each batch has 10 questions from this topic, in order. Take them one by one to work through all 50 MCQs. Login to save your scores and see your best per batch.
Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.
- Q1Past Paper · PPSC/FPSC/NTSeasy
Comparative statement of tenders shows
💡 Explanation:Employer compares responsive bids for award
- Q2Past Paper · PPSC/FPSC/NTSeasy
Comparative statement of tenders shows
💡 Explanation:Employer compares responsive bids for award
- Q3medium
Bill of materials differs from BOQ by listing
💡 Explanation:BOM for procurement; BOQ for construction contract
- Q4easy
Taking off quantities means
💡 Explanation:Manual or software extraction of lengths areas volumes
- Q5Past Paper · PPSC/FPSC/NTSeasy
Quantity surveyor role includes
💡 Explanation:QS manages cost from estimate to final account
- Q6hard
Percentage rate contract pays
💡 Explanation:Less common now; lump sum and unit price preferred
- Q7Past Paper · PPSC/FPSC/NTSeasy
Schedule of rates SOR issued by
💡 Explanation:PWD irrigation use SOR for petty contracts
- Q8easy
Overhead and profit added to
💡 Explanation:Contractor recovers site office margin in rates
- Q9Past Paper · PPSC/FPSC/NTSmedium
Lead and lift charges in rate analysis cover
💡 Explanation:Distance vertical lift add to material cost
- Q10medium
Earthwork in estimate measured by
💡 Explanation:Shrinkage swell factors apply between bank and loose
- Q11Past Paper · PPSC/FPSC/NTSeasy
Reinforcement quantity taken as
💡 Explanation:BBS from drawings multiplied by unit weight
- Q12easy
Unit of measurement for brick masonry commonly
💡 Explanation:Spec defines whether volume or area basis
- Q13medium
Long wall short wall method used in
💡 Explanation:Long walls and short walls measured separately
- Q14medium
Centre line method suits
💡 Explanation:Mean length times breadth height for walls
- Q15Past Paper · PPSC/FPSC/NTSeasy
Plinth area estimate used for
💡 Explanation:Quick cost per square foot based on plinth area
- Q16medium
Measurement rules for concrete may be
💡 Explanation:Standard rules avoid disputes in payment
- Q17Past Paper · PPSC/FPSC/NTSmedium
Cost-benefit analysis compares
💡 Explanation:Public projects use CBA for economic justification
- Q18easy
Payback period measures
💡 Explanation:Simple metric ignoring cash flows after payback
- Q19Past Paper · PPSC/FPSC/NTSmedium
IRR is discount rate when
💡 Explanation:Internal rate of return compared to hurdle rate
- Q20Past Paper · PPSC/FPSC/NTSmedium
NPV positive means
💡 Explanation:Net present value sums discounted cash flows
- Q21Past Paper · PPSC/FPSC/NTSeasy
Feasibility study determines
💡 Explanation:Go/no-go decision before detailed design
- Q22easy
Project life cycle phases include
💡 Explanation:Standard PM lifecycle for infrastructure
- Q23Past Paper · PPSC/FPSC/NTSmedium
Escalation clause in contract adjusts
💡 Explanation:Multi-year projects need price adjustment mechanism
- Q24Past Paper · PPSC/FPSC/NTSmedium
Contingency allowance covers
💡 Explanation:Typically 5-15% depending on design completeness
- Q25Past Paper · PPSC/FPSC/NTSeasy
Tender documents package includes
💡 Explanation:Complete package defines scope for bidding
- Q26Past Paper · PPSC/FPSC/NTSmedium
BOQ preparation requires
💡 Explanation:PCEM or CESMM style rules ensure comparable tenders
- Q27Past Paper · PPSC/FPSC/NTSeasy
Detailed estimate prepared from
💡 Explanation:Quantities measured per standard methods for accuracy
- Q28Past Paper · PPSC/FPSC/NTSeasy
Abstract of cost links
💡 Explanation:Abstract is financial summary of estimate
- Q29Past Paper · PPSC/FPSC/NTSmedium
Rate analysis for excavation includes
💡 Explanation:Unit rate built from material labour plant analysis
- Q30medium
Depreciation of equipment in rate analysis accounts for
💡 Explanation:Ownership cost spread over useful operating hours
- Q31Past Paper · PPSC/FPSC/NTSmedium
Lowest bid not always accepted if
💡 Explanation:PPRA allows rejection with recorded justification
- Q32hard
Earned value in cost control compares
💡 Explanation:EVM integrates scope schedule cost
- Q33medium
Final account settles
💡 Explanation:Agreed final payment closes contract financially
- Q34medium
Daywork in contract pays
💡 Explanation:Used for unforeseen minor work by employer direction
- Q35medium
Provisional sum covers
💡 Explanation:Later instructed work valued per contract rules
- Q36hard
Prime cost sum for
💡 Explanation:PC sum with contractor attendance fee
- Q37hard
Cost plan during design stages RIBA or similar refines
💡 Explanation:Cost planning tracks budget through design development
- Q38medium
Benchmarking project cost uses
💡 Explanation:Historical data adjusts for location time scope
- Q39easy
S-curve cash flow for owner shows
💡 Explanation:Front heavy or balanced spending affects financing
- Q40medium
Benefit-cost ratio greater than one indicates
💡 Explanation:BCR used in economic appraisal of public works
- Q41hard
Sensitivity analysis tests
💡 Explanation:NPV tested against cost overrun demand shortfall
- Q42hard
Shadow price in economic analysis reflects
💡 Explanation:Public sector uses shadow pricing for labour capital forex
- Q43Past Paper · PPSC/FPSC/NTSmedium
Land acquisition cost in feasibility includes
💡 Explanation:ROW cost significant for highways transmission lines
- Q44medium
Operation and maintenance cost in lifecycle includes
💡 Explanation:LCCA compares alternatives over 20-50 years
- Q45easy
Quantity takeoff software examples
💡 Explanation:Digital measurement from PDF CAD models
- Q46medium
Standard method of measurement avoids
💡 Explanation:Consistent rules fair to employer and contractor
- Q47medium
Cut and fill balance in earthwork estimate aims to
💡 Explanation:Mass diagram optimizes earthwork cost
- Q48hard
Star rates in contract are
💡 Explanation:Contract defines procedure to agree star rates
- Q49medium
Price adjustment formula uses
💡 Explanation:Linked to inflation indices in long contracts
- Q50Past Paper · PPSC/FPSC/NTSeasy
Work charged to contractor measured by
💡 Explanation:Engineer certifies quantities for IPC