Project Planning and Quantity Surveying MCQs 2026

50 questions with detailed answers · 21 from past papers · 5 quiz batches available

📚 Civil Engineering📄 21 Past-Paper Qs✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1Questions 1–10 of 50
  1. Q1Past Paper · PPSC/FPSC/NTSeasy

    Comparative statement of tenders shows

    1. AOnly weather data
    2. BOnly cricket scores
    3. COnly staff birthdays
    4. DRates and amounts from each bidder ranked
    💡 Explanation:

    Employer compares responsive bids for award

  2. Q2Past Paper · PPSC/FPSC/NTSeasy

    Comparative statement of tenders shows

    1. AOnly weather data
    2. BOnly cricket scores
    3. COnly staff birthdays
    4. DRates and amounts from each bidder ranked
    💡 Explanation:

    Employer compares responsive bids for award

  3. Q3medium

    Bill of materials differs from BOQ by listing

    1. AOnly staff salaries
    2. BOnly land price always
    3. CMaterials without full labour plant breakdown
    4. DOnly legal fees only
    💡 Explanation:

    BOM for procurement; BOQ for construction contract

  4. Q4easy

    Taking off quantities means

    1. ARemoving building parts physically
    2. BMeasuring from drawings to calculate work amounts
    3. COnly painting walls
    4. DOnly deleting files
    💡 Explanation:

    Manual or software extraction of lengths areas volumes

  5. Q5Past Paper · PPSC/FPSC/NTSeasy

    Quantity surveyor role includes

    1. AOnly structural design always
    2. BOnly soil testing always
    3. COnly driving train
    4. DMeasurement valuation and contract administration
    💡 Explanation:

    QS manages cost from estimate to final account

  6. Q6hard

    Percentage rate contract pays

    1. AFixed lump sum only always
    2. BPercentage over measured cost or defined basis
    3. CZero documentation
    4. DOnly bonus without work
    💡 Explanation:

    Less common now; lump sum and unit price preferred

  7. Q7Past Paper · PPSC/FPSC/NTSeasy

    Schedule of rates SOR issued by

    1. AGovernment department for small works
    2. BRandom shopkeeper
    3. COnly cricket board
    4. DOnly airline
    💡 Explanation:

    PWD irrigation use SOR for petty contracts

  8. Q8easy

    Overhead and profit added to

    1. AOnly client furniture
    2. BOnly government tax always same as overhead
    3. CDirect cost for contractor unit rate
    4. DOnly discount subtracted always
    💡 Explanation:

    Contractor recovers site office margin in rates

  9. Q9Past Paper · PPSC/FPSC/NTSmedium

    Lead and lift charges in rate analysis cover

    1. AOnly profit tax
    2. BOnly design fee
    3. COnly insurance of car
    4. DTransport and hoisting of materials
    💡 Explanation:

    Distance vertical lift add to material cost

  10. Q10medium

    Earthwork in estimate measured by

    1. AOnly truck count without volume
    2. BBank measure or loose cubic metre per spec
    3. COnly colour of soil
    4. DOnly smell of soil
    💡 Explanation:

    Shrinkage swell factors apply between bank and loose

  11. Q11Past Paper · PPSC/FPSC/NTSeasy

    Reinforcement quantity taken as

    1. ALength in kilometres only without weight
    2. BCount of workers
    3. CWeight in kg or tonnes from bar schedule
    4. DVolume of concrete ignored always
    💡 Explanation:

    BBS from drawings multiplied by unit weight

  12. Q12easy

    Unit of measurement for brick masonry commonly

    1. ACubic metre or per square metre wall
    2. BKilometre length only
    3. CLitre volume only for all
    4. DTonnes always only
    💡 Explanation:

    Spec defines whether volume or area basis

  13. Q13medium

    Long wall short wall method used in

    1. ACircular tank only always
    2. BOnly highway ESAL
    3. CBuilding with varying wall lengths
    4. DOnly airport runway
    💡 Explanation:

    Long walls and short walls measured separately

  14. Q14medium

    Centre line method suits

    1. ARegular symmetric walls and trenches
    2. BIrregular scattered footings only always
    3. COnly paint work
    4. DOnly landscaping only
    💡 Explanation:

    Mean length times breadth height for walls

  15. Q15Past Paper · PPSC/FPSC/NTSeasy

    Plinth area estimate used for

    1. AFinal contractor payment without detail
    2. BHarbour dredging quantity
    3. CRailway signalling
    4. DRough cost of buildings early stage
    💡 Explanation:

    Quick cost per square foot based on plinth area

  16. Q16medium

    Measurement rules for concrete may be

    1. ABy guess bags only
    2. BBy cubic metre in place net of openings
    3. CBy surface paint area only
    4. DBy weight of rebar only without concrete
    💡 Explanation:

    Standard rules avoid disputes in payment

  17. Q17Past Paper · PPSC/FPSC/NTSmedium

    Cost-benefit analysis compares

    1. APresent value of benefits and costs
    2. BOnly contractor mood
    3. COnly soil colour
    4. DOnly wind rose
    💡 Explanation:

    Public projects use CBA for economic justification

  18. Q18easy

    Payback period measures

    1. ATotal project life always
    2. BOnly design phase
    3. CTime to recover initial investment
    4. DOnly maintenance only
    💡 Explanation:

    Simple metric ignoring cash flows after payback

  19. Q19Past Paper · PPSC/FPSC/NTSmedium

    IRR is discount rate when

    1. ACost equals zero always
    2. BNPV equals zero
    3. CBenefit undefined
    4. DTax equals zero only
    💡 Explanation:

    Internal rate of return compared to hurdle rate

  20. Q20Past Paper · PPSC/FPSC/NTSmedium

    NPV positive means

    1. AAlways loss
    2. BBreak even only always
    3. CIgnore time value of money
    4. DProject returns exceed discount rate
    💡 Explanation:

    Net present value sums discounted cash flows

  21. Q21Past Paper · PPSC/FPSC/NTSeasy

    Feasibility study determines

    1. AOnly paint schedule
    2. BOnly staff lunch menu
    3. CTechnical economic and financial viability
    4. DOnly logo design only
    💡 Explanation:

    Go/no-go decision before detailed design

  22. Q22easy

    Project life cycle phases include

    1. AOnly excavation always
    2. BInitiation planning execution closure
    3. COnly painting always
    4. DOnly demolition only
    💡 Explanation:

    Standard PM lifecycle for infrastructure

  23. Q23Past Paper · PPSC/FPSC/NTSmedium

    Escalation clause in contract adjusts

    1. AFixed price forever without change ever
    2. BOnly contractor hobby costs
    3. COnly paint colour change
    4. DRates for inflation over long execution period
    💡 Explanation:

    Multi-year projects need price adjustment mechanism

  24. Q24Past Paper · PPSC/FPSC/NTSmedium

    Contingency allowance covers

    1. AUnforeseen work within project scope
    2. BKnown BOQ items priced twice
    3. CContractor profit guarantee
    4. DTax bribe illegal item
    💡 Explanation:

    Typically 5-15% depending on design completeness

  25. Q25Past Paper · PPSC/FPSC/NTSeasy

    Tender documents package includes

    1. AOnly oral quote
    2. BInstructions drawings specs BOQ and conditions
    3. COnly one sketch
    4. DOnly email hello
    💡 Explanation:

    Complete package defines scope for bidding

  26. Q26Past Paper · PPSC/FPSC/NTSmedium

    BOQ preparation requires

    1. ARandom units mixed without rule
    2. BOnly lump descriptions without qty
    3. CStandard method of measurement for items
    4. DOnly photographs
    💡 Explanation:

    PCEM or CESMM style rules ensure comparable tenders

  27. Q27Past Paper · PPSC/FPSC/NTSeasy

    Detailed estimate prepared from

    1. ADrawings specifications and site measurements
    2. BOnly guess without quantity
    3. COnly contractor mood
    4. DOnly weather forecast
    💡 Explanation:

    Quantities measured per standard methods for accuracy

  28. Q28Past Paper · PPSC/FPSC/NTSeasy

    Abstract of cost links

    1. AOnly site diary
    2. BBOQ quantities rates and amounts
    3. COnly labour names
    4. DOnly vehicle log
    💡 Explanation:

    Abstract is financial summary of estimate

  29. Q29Past Paper · PPSC/FPSC/NTSmedium

    Rate analysis for excavation includes

    1. AOnly profit without cost
    2. BOnly tax without items
    3. COnly contingency only
    4. DLabour equipment and overhead for one unit
    💡 Explanation:

    Unit rate built from material labour plant analysis

  30. Q30medium

    Depreciation of equipment in rate analysis accounts for

    1. AWear and tear allocation per hour
    2. BFuel colour change
    3. COperator uniform
    4. DOffice rent unrelated
    💡 Explanation:

    Ownership cost spread over useful operating hours

  31. Q31Past Paper · PPSC/FPSC/NTSmedium

    Lowest bid not always accepted if

    1. AAlways must accept lowest legally always without check
    2. BNon-responsive or abnormally low risking performance
    3. COnly highest accepted always
    4. DRandom selection
    💡 Explanation:

    PPRA allows rejection with recorded justification

  32. Q32hard

    Earned value in cost control compares

    1. ABudgeted cost of work performed to actual
    2. BOnly invoice date
    3. COnly staff age
    4. DOnly vehicle colour
    💡 Explanation:

    EVM integrates scope schedule cost

  33. Q33medium

    Final account settles

    1. AOnly bid bond return without measurement
    2. BOnly mobilization without completion
    3. COnly design fee unrelated
    4. DContract sum adjustments variations claims
    💡 Explanation:

    Agreed final payment closes contract financially

  34. Q34medium

    Daywork in contract pays

    1. ALump sum regardless of hours
    2. BZero payment always
    3. CLabour plant materials at schedule rates plus percentage
    4. DOnly profit without work
    💡 Explanation:

    Used for unforeseen minor work by employer direction

  35. Q35medium

    Provisional sum covers

    1. ANothing defined ever
    2. BDefined scope with uncertain detail at tender
    3. CContractor illegal payment
    4. DOnly tax evasion
    💡 Explanation:

    Later instructed work valued per contract rules

  36. Q36hard

    Prime cost sum for

    1. AFree unlimited gift
    2. BOnly main contractor profit alone
    3. CNominated subcontract supply later adjusted
    4. DOnly design change without record
    💡 Explanation:

    PC sum with contractor attendance fee

  37. Q37hard

    Cost plan during design stages RIBA or similar refines

    1. AEstimate at concept schematic detailed stages
    2. BOnly after demolition
    3. COnly before idea
    4. DOnly never updated
    💡 Explanation:

    Cost planning tracks budget through design development

  38. Q38medium

    Benchmarking project cost uses

    1. AOnly random number
    2. BOnly lottery
    3. COnly horoscope
    4. DSimilar completed projects indices
    💡 Explanation:

    Historical data adjusts for location time scope

  39. Q39easy

    S-curve cash flow for owner shows

    1. AOnly soil gradation
    2. BExpenditure profile over project duration
    3. COnly wind data
    4. DOnly tide chart
    💡 Explanation:

    Front heavy or balanced spending affects financing

  40. Q40medium

    Benefit-cost ratio greater than one indicates

    1. ABenefits exceed costs in present value terms
    2. BProject always unviable
    3. CEqual ignore decision always
    4. DOnly costs matter
    💡 Explanation:

    BCR used in economic appraisal of public works

  41. Q41hard

    Sensitivity analysis tests

    1. AOnly one fixed scenario always
    2. BOnly paint colour
    3. COnly staff names
    4. DEffect of variable changes on viability
    💡 Explanation:

    NPV tested against cost overrun demand shortfall

  42. Q42hard

    Shadow price in economic analysis reflects

    1. AMarket price always identical without adjustment
    2. BZero always
    3. CTrue social opportunity cost
    4. DContractor bid only
    💡 Explanation:

    Public sector uses shadow pricing for labour capital forex

  43. Q43Past Paper · PPSC/FPSC/NTSmedium

    Land acquisition cost in feasibility includes

    1. ACompensation resettlement and delays
    2. BOnly free land always assumed
    3. COnly interior design
    4. DOnly signage
    💡 Explanation:

    ROW cost significant for highways transmission lines

  44. Q44medium

    Operation and maintenance cost in lifecycle includes

    1. AOnly capital cost day one only forever ignored
    2. BOnly paint once
    3. CStaff energy repairs over service life
    4. DOnly foundation only
    💡 Explanation:

    LCCA compares alternatives over 20-50 years

  45. Q45easy

    Quantity takeoff software examples

    1. AOnly word processor
    2. BOnly music player
    3. COnly game engine
    4. DBluebeam CostX Cubit
    💡 Explanation:

    Digital measurement from PDF CAD models

  46. Q46medium

    Standard method of measurement avoids

    1. AAll ambiguity intentionally
    2. BAmbiguity in item description and unit
    3. COnly verbal contracts
    4. DOnly lump sum without scope
    💡 Explanation:

    Consistent rules fair to employer and contractor

  47. Q47medium

    Cut and fill balance in earthwork estimate aims to

    1. AMaximize haul distance always
    2. BIgnore topography
    3. CImport all soil from abroad always joke item
    4. DMinimize borrow and waste haul
    💡 Explanation:

    Mass diagram optimizes earthwork cost

  48. Q48hard

    Star rates in contract are

    1. AIllegal always
    2. BSame as tender rates always without process
    3. CNew rates agreed for varied work not in BOQ
    4. DOnly penalty rates
    💡 Explanation:

    Contract defines procedure to agree star rates

  49. Q49medium

    Price adjustment formula uses

    1. AContractor arbitrary invoice always
    2. BOfficial indices for materials labour fuel
    3. COnly gold price alone always
    4. DOnly cricket ranking
    💡 Explanation:

    Linked to inflation indices in long contracts

  50. Q50Past Paper · PPSC/FPSC/NTSeasy

    Work charged to contractor measured by

    1. AEngineer per contract method
    2. BContractor alone without check always
    3. CRandom guess
    4. DSocial media vote
    💡 Explanation:

    Engineer certifies quantities for IPC