- Q1Past Paper · PPSC/FPSC/CSSmedium
Transmission losses in Pakistan are reduced by operating at higher voltage for the same MW transfer
💡 Explanation:For a given power, higher voltage reduces current and I-squared-R losses.
- Q2medium
Distributed generation includes smaller plants connected at distribution voltage levels
💡 Explanation:DG can be renewables, cogeneration, or small thermal near load centers.
- Q3Past Paper · PPSC/FPSC/CSSeasy
In a Rankine cycle the working fluid undergoes isentropic expansion in the turbine
💡 Explanation:The ideal Rankine cycle includes isentropic expansion in the turbine after heat addition in the boiler.
- Q4easy
The boiler in a thermal power plant converts chemical energy of fuel into thermal energy of steam
💡 Explanation:Boilers burn fuel to produce high-pressure, high-temperature steam for the turbine.
- Q5Past Paper · PPSC/FPSC/CSSmedium
Increasing condenser vacuum generally improves thermal plant efficiency
💡 Explanation:Lower condenser pressure reduces turbine exhaust enthalpy and increases useful work per unit heat input.
- Q6easy
The function of a condenser in a steam power plant is to reject heat and condense exhaust steam
💡 Explanation:The condenser maintains low back pressure at the turbine exhaust and returns condensate to the boiler feed system.
- Q7medium
Overall thermal plant efficiency is typically highest for combined cycle gas turbine plants among conventional thermal options
💡 Explanation:CCGT captures waste heat from the gas turbine in a steam bottoming cycle, raising overall efficiency.
- Q8Past Paper · PPSC/FPSC/CSSmedium
Reheat in a Rankine cycle is used to reduce moisture at the turbine exhaust and improve efficiency
💡 Explanation:Reheating raises average heat addition temperature and limits wetness in later turbine stages.
- Q9medium
Regeneration in a steam cycle uses extracted steam to preheat feedwater before the boiler
💡 Explanation:Feedwater heaters recover internal energy from turbine bleeds, improving cycle efficiency.
- Q10medium
Power purchase agreements define tariff, capacity obligations, and dispatch rules for IPPs
💡 Explanation:PPAs provide revenue certainty and outline take-or-pay or energy payment structures.
- Q11easy
The turbine in a thermal plant converts enthalpy drop of steam into mechanical shaft work
💡 Explanation:Steam expands through turbine blades producing torque on the generator shaft.
- Q12Past Paper · PPSC/FPSC/CSSmedium
Boiler efficiency is defined as energy absorbed by water-steam divided by energy supplied by fuel
💡 Explanation:Boiler efficiency measures how effectively fuel energy is transferred to the working fluid.
- Q13easy
A superheater raises steam temperature above saturation at constant pressure in the boiler
💡 Explanation:Superheated steam reduces turbine blade erosion and improves thermal efficiency.
- Q14medium
Net plant heat rate is inversely related to plant efficiency
💡 Explanation:Heat rate in kJ/kWh equals 3600 divided by efficiency; lower heat rate means higher efficiency.
- Q15Past Paper · PPSC/FPSC/CSSmedium
An economizer preheats feedwater using flue gas heat before it enters the boiler drum
💡 Explanation:Economizers recover waste heat from exhaust gases improving overall plant efficiency.
- Q16medium
Carnot efficiency sets the theoretical upper limit for any heat engine operating between two reservoirs
💡 Explanation:Maximum efficiency depends on source and sink temperatures: 1 minus Tcold over Thot.
- Q17easy
A deaerator removes dissolved oxygen and non-condensable gases from boiler feedwater
💡 Explanation:Oxygen causes corrosion and pitting in boiler tubes and turbine components.
- Q18Past Paper · PPSC/FPSC/CSShard
The pressure ratio across the turbine stages determines the enthalpy drop available for work
💡 Explanation:Greater allowable pressure drop across stages increases specific work output per kg of steam.
- Q19easy
Hydraulic head in a hydro plant is the vertical height through which water falls to produce energy
💡 Explanation:Potential energy per unit weight equals head times gravitational acceleration in standard formulations.
- Q20medium
Plant factor or capacity factor equals actual energy output divided by maximum possible output at rated capacity
💡 Explanation:Capacity factor reflects how fully a plant is utilized over time.
- Q21medium
An annual load duration curve arranges loads in descending order of magnitude over the year
💡 Explanation:It helps estimate energy at various load levels and duration of peaks.
- Q22hard
Coincidence factor is the reciprocal of diversity factor in load calculations
💡 Explanation:Coincidence factor equals maximum combined demand divided by sum of individual maxima.
- Q23medium
Load factor of the system helps determine total energy sales and generation requirements
💡 Explanation:Energy equals average load times hours which links directly to load factor.
- Q24Past Paper · PPSC/FPSC/CSSmedium
Peak-to-valley ratio on a daily curve influences spinning reserve and peaking plant needs
💡 Explanation:Large swings require flexible capacity and reserve margins.
- Q25hard
Demand factor is ratio of maximum demand of a group to connected load of that group
💡 Explanation:Demand factor indicates how much of connected load is actually demanded at peak.
- Q26Past Paper · PPSC/FPSC/CSSeasy
WAPDA historically played a central role in developing and operating major public hydel power in Pakistan
💡 Explanation:WAPDA built and operates large dams and hydel stations like Tarbela and Mangla.
- Q27easy
NTDC is responsible for bulk electric power transmission across Pakistan
💡 Explanation:National Transmission and Despatch Company operates the high-voltage national grid.
- Q28Past Paper · PPSC/FPSC/CSSeasy
Tarbela Dam is among the largest hydel power sources in Pakistan on the Indus River
💡 Explanation:Tarbela provides substantial peaking and energy storage through its reservoir.
- Q29easy
Mangla Dam on the Jhelum River contributes significant hydel generation for the national grid
💡 Explanation:Mangla is a major storage project supporting Punjab and national demand.
- Q30Past Paper · PPSC/FPSC/CSSmedium
Ghazi Barotha is a run-of-river hydel project on the Indus downstream of Tarbela
💡 Explanation:Ghazi Barotha uses canal tunnel flow for large base hydel output.
- Q31medium
Hydel power historically forms a major share of Pakistan installed generation capacity
💡 Explanation:Hydel from Tarbela, Mangla, Ghazi Barotha and others remains a key renewable base.
- Q32medium
Independent Power Producers sell electricity to the grid often under power purchase agreements
💡 Explanation:IPPs expanded thermal capacity especially in the 1990s and beyond.
- Q33Past Paper · PPSC/FPSC/CSSmedium
NEECA promotes energy conservation and efficiency standards in Pakistan
💡 Explanation:National Energy Efficiency and Conservation Authority drives demand-side efficiency policy.
- Q34medium
Grid code defines technical requirements for connecting generators and loads to the power system
💡 Explanation:Grid codes cover voltage, frequency, fault ride-through, and protection standards.
- Q35Past Paper · PPSC/FPSC/CSSmedium
Merit order dispatch schedules generators from lowest to highest marginal cost until demand is met
💡 Explanation:Economic dispatch minimizes fuel cost by using cheapest incremental generation first.
- Q36medium
Spinning reserve is online capacity that can respond quickly to frequency drops or generator trips
💡 Explanation:Spinning reserve maintains reliability during contingencies without long startup delay.
- Q37hard
Economic dispatch minimizes total generation cost subject to demand and network constraints
💡 Explanation:Lambda iteration and similar methods balance incremental costs across committed units.
- Q38Past Paper · PPSC/FPSC/CSSeasy
Frequency of 50 Hz on the Pakistan grid must be maintained by matching generation and load
💡 Explanation:Generation-load imbalance causes frequency deviation triggering control and reserves.
- Q39medium
A cold reserve unit is not synchronized and requires startup time before contributing power
💡 Explanation:Cold reserves are cheaper to maintain but slower than spinning reserve.
- Q40medium
Cogeneration produces both electricity and useful heat from the same fuel input
💡 Explanation:Combined heat and power achieves high overall fuel utilization efficiency.
- Q41easy
A penstock is a pipe or conduit that conveys water from the reservoir to the turbine
💡 Explanation:Penstocks must withstand surge pressures and deliver design flow to the powerhouse.
- Q42Past Paper · PPSC/FPSC/CSSmedium
Francis turbines are commonly used for medium head hydro installations
💡 Explanation:Francis turbines suit roughly 40 to 400 meters head with moderate to high flow.
- Q43medium
Pelton turbines use impulse buckets and are suited to high head low flow sites
💡 Explanation:Pelton wheels convert high-velocity jets into mechanical energy at heads often above 300 m.
- Q44medium
Kaplan turbines are propeller-type machines suited to low head high flow conditions
💡 Explanation:Kaplan runners have adjustable blades for efficiency over varying river flows.
- Q45Past Paper · PPSC/FPSC/CSSeasy
Run-of-river hydro plants have limited storage and follow the natural inflow of the river
💡 Explanation:They rely on continuous river flow rather than large seasonal reservoirs.
- Q46easy
Storage hydro plants can shift energy production from wet season to dry season using reservoirs
💡 Explanation:Reservoirs store potential energy for peaking and seasonal balancing.
- Q47medium
Hydro power output is proportional to head times flow times efficiency in simplified form
💡 Explanation:Power approximately equals rho g Q H eta for idealized analysis.
- Q48easy
The powerhouse in a hydro plant houses turbines, generators, and auxiliary equipment
💡 Explanation:Mechanical energy conversion to electricity occurs in the powerhouse.
- Q49Past Paper · PPSC/FPSC/CSShard
A surge tank dampens pressure transients in long penstocks during load changes
💡 Explanation:Surge tanks absorb kinetic energy of moving water columns during rapid valve action.
- Q50hard
Specific speed helps select the appropriate hydro turbine type for a given head and flow
💡 Explanation:Specific speed correlates runner geometry with site hydraulic conditions.
- Q51medium
Pumped storage hydro uses off-peak electricity to pump water to an upper reservoir for later generation
💡 Explanation:It acts as energy storage by converting electrical to potential energy and back.
- Q52Past Paper · PPSC/FPSC/CSSeasy
Nuclear power generation relies on controlled nuclear fission of heavy fuel nuclei
💡 Explanation:Fission splits nuclei like U-235 releasing heat via neutron chain reactions.
- Q53medium
In a PWR the primary coolant water is kept under high pressure to remain subcooled
💡 Explanation:High pressure prevents bulk boiling in the pressurized water reactor primary loop.
- Q54Past Paper · PPSC/FPSC/CSSmedium
In a BWR water boils directly in the reactor vessel to produce steam for the turbine
💡 Explanation:BWR steam is radioactive so turbines and associated systems are within containment considerations.
- Q55easy
Control rods in a nuclear reactor absorb neutrons to regulate reactivity and power level
💡 Explanation:Inserting rods reduces neutron flux and shuts down or lowers reactor power.
- Q56medium
The moderator in thermal reactors slows fast neutrons to improve fission probability in fuel
💡 Explanation:Light water in PWR and BWR serves as both coolant and moderator.
- Q57medium
Nuclear fuel enrichment for commercial LWRs increases the fraction of fissile U-235
💡 Explanation:Natural uranium is about 0.7 percent U-235; LWR fuel is enriched to several percent.
- Q58easy
Containment structures in nuclear plants limit release of radioactivity during accidents
💡 Explanation:Containment provides a barrier against fission product escape to the environment.
- Q59Past Paper · PPSC/FPSC/CSShard
Decay heat after reactor shutdown must still be removed to prevent fuel damage
💡 Explanation:Fission product decay continues producing heat requiring residual heat removal systems.
- Q60easy
A daily load curve shows variation of power demand over a 24-hour period
💡 Explanation:Daily curves reveal peak and off-peak periods for planning and dispatch.
- Q61Past Paper · PPSC/FPSC/CSSeasy
Base load is the relatively constant minimum demand sustained over long periods
💡 Explanation:Base load plants run continuously to serve the flat portion of the load curve.
- Q62easy
Peak load occurs at maximum demand and is typically served by peaking or flexible plants
💡 Explanation:Peaking units may include gas turbines, hydro peakers, or stored energy resources.
- Q63medium
Load factor equals average load divided by maximum load over a given period
💡 Explanation:Higher load factor indicates more uniform utilization of capacity.
- Q64Past Paper · PPSC/FPSC/CSSmedium
Diversity factor is the ratio of sum of individual maximum demands to the maximum of the combined demand
💡 Explanation:Diversity factor is not less than unity because peaks seldom coincide across all consumers.
- Q65Past Paper · PPSC/FPSC/CSShard
Must-run status may be assigned to hydel or renewable plants due to zero or low marginal fuel cost
💡 Explanation:Low marginal cost units are dispatched first when technically available.
- Q66hard
Automatic generation control adjusts generator output to restore frequency and scheduled interchange
💡 Explanation:AGC uses tie-line bias control to correct area control error.
- Q67easy
The national grid integrates generation from hydel thermal nuclear and renewable sources across DISCO areas
💡 Explanation:NTDC coordinates bulk transfer; distribution companies serve end consumers.
- Q68Past Paper · PPSC/FPSC/CSSmedium
Peaking hydro units can start quickly compared to large coal steam units
💡 Explanation:Hydel governors can ramp output within minutes supporting peak and reserve roles.
- Q69medium
Reactive power support is necessary for voltage control and is not the same as real power MW
💡 Explanation:Generators and compensators supply MVAR to maintain acceptable voltage profiles.
- Q70medium
A forced outage reduces available plant capacity unexpectedly due to equipment failure
💡 Explanation:Forced outage rate is a key reliability indicator for generation planning.