Capital Budgeting MCQs 2026

75 questions with detailed answers · 29 from past papers · 8 quiz batches available

📚 Finance📄 29 Past-Paper Qs✓ Free · No Login Needed
🎯 Mock Test

Read each question, think about the answer, then click Show Answer to reveal the correct option and explanation. Load 10 at a time so it stays manageable — perfect for one-topic study sessions on the bus or during a break.

Page 1 of 1Questions 1–10 of 75
  1. Q1Past Paper · PPSC/FPSC/NTShard

    NPV exercise 60: initial cost Rs 803,000, annual inflow Rs 136,200 for 7 years, discount rate 12%. NPV is approximately

    1. ARs -181,416
    2. BRs 621,584
    3. CRs -803,000
    4. DRs -221,416
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  2. Q2hard

    Capital budgeting analysis 19 for warehouse automation project must correctly treat depreciation tax shield by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dadding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 19: depreciation tax shield for warehouse automation.

  3. Q3hard

    NPV exercise 18: initial cost Rs 299,000, annual inflow Rs 56,600 for 5 years, discount rate 10%. NPV is approximately

    1. ARs 214,559
    2. BRs -84,441
    3. CRs -299,000
    4. DRs -124,441
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  4. Q4Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 17 for solar power plant project must correctly treat depreciation tax shield by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dadding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 17: depreciation tax shield for solar power plant.

  5. Q5hard

    NPV exercise 16: initial cost Rs 265,000, annual inflow Rs 49,000 for 3 years, discount rate 16%. NPV is approximately

    1. ARs -154,951
    2. BRs 110,049
    3. CRs -265,000
    4. DRs -194,951
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  6. Q6medium

    Capital budgeting analysis 15 for waste treatment facility project must correctly treat working capital recovery in terminal year by

    1. Acapitalizing all historical costs into initial outlay
    2. Badding back net working capital release at project end
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 15: working capital recovery in terminal year for waste treatment facility.

  7. Q7Past Paper · PPSC/FPSC/NTShard

    NPV exercise 14: initial cost Rs 266,000, annual inflow Rs 51,400 for 6 years, discount rate 14%. NPV is approximately

    1. ARs 199,878
    2. BRs -266,000
    3. CRs -106,122
    4. DRs -66,122
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  8. Q8hard

    Capital budgeting analysis 13 for ERP system project must correctly treat working capital recovery in terminal year by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dadding back net working capital release at project end
    💡 Explanation:

    Project 13: working capital recovery in terminal year for ERP system.

  9. Q9hard

    NPV exercise 12: initial cost Rs 232,000, annual inflow Rs 43,800 for 4 years, discount rate 12%. NPV is approximately

    1. ARs -98,964
    2. BRs 133,036
    3. CRs -232,000
    4. DRs -138,964
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  10. Q10Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 11 for warehouse automation project must correctly treat working capital recovery in terminal year by

    1. Acapitalizing all historical costs into initial outlay
    2. Badding back net working capital release at project end
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 11: working capital recovery in terminal year for warehouse automation.

  11. Q11hard

    NPV exercise 10: initial cost Rs 198,000, annual inflow Rs 46,200 for 7 years, discount rate 10%. NPV is approximately

    1. ARs 224,921
    2. BRs 26,921
    3. CRs -198,000
    4. DRs -13,079
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  12. Q12Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 9 for solar power plant project must correctly treat working capital recovery in terminal year by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cadding back net working capital release at project end
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 9: working capital recovery in terminal year for solar power plant.

  13. Q13hard

    NPV exercise 8: initial cost Rs 164,000, annual inflow Rs 38,600 for 5 years, discount rate 16%. NPV is approximately

    1. ARs -37,612
    2. BRs 126,388
    3. CRs -164,000
    4. DRs -77,612
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  14. Q14hard

    Capital budgeting analysis 7 for waste treatment facility project must correctly treat salvage value estimation by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cincluding after-tax salvage in terminal year cash flow
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 7: salvage value estimation for waste treatment facility.

  15. Q15Past Paper · PPSC/FPSC/NTShard

    NPV exercise 6: initial cost Rs 165,000, annual inflow Rs 31,000 for 3 years, discount rate 14%. NPV is approximately

    1. ARs -93,029
    2. BRs 71,971
    3. CRs -165,000
    4. DRs -133,029
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  16. Q16medium

    Capital budgeting analysis 5 for ERP system project must correctly treat salvage value estimation by

    1. Aincluding after-tax salvage in terminal year cash flow
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 5: salvage value estimation for ERP system.

  17. Q17hard

    NPV exercise 4: initial cost Rs 131,000, annual inflow Rs 33,400 for 6 years, discount rate 12%. NPV is approximately

    1. ARs 137,321
    2. BRs -131,000
    3. CRs -33,679
    4. DRs 6,321
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  18. Q18Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 3 for warehouse automation project must correctly treat salvage value estimation by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cincluding after-tax salvage in terminal year cash flow
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 3: salvage value estimation for warehouse automation.

  19. Q19hard

    NPV exercise 2: initial cost Rs 97,000, annual inflow Rs 25,800 for 4 years, discount rate 10%. NPV is approximately

    1. ARs 81,783
    2. BRs -97,000
    3. CRs -55,217
    4. DRs -15,217
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  20. Q20hard

    Capital budgeting analysis 1 for solar power plant project must correctly treat salvage value estimation by

    1. Aincluding after-tax salvage in terminal year cash flow
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 1: salvage value estimation for solar power plant.

  21. Q21medium

    Capital budgeting analysis 57 for solar power plant project must correctly treat mutually exclusive replacement choice by

    1. Acapitalizing all historical costs into initial outlay
    2. Bcomparing incremental cash flows of new versus continuing old equipment
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 57: mutually exclusive replacement choice for solar power plant.

  22. Q22medium

    Capital budgeting analysis 59 for warehouse automation project must correctly treat mutually exclusive replacement choice by

    1. Acapitalizing all historical costs into initial outlay
    2. Bcomparing incremental cash flows of new versus continuing old equipment
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 59: mutually exclusive replacement choice for warehouse automation.

  23. Q23hard

    NPV exercise 44: initial cost Rs 601,000, annual inflow Rs 105,400 for 6 years, discount rate 12%. NPV is approximately

    1. ARs 433,342
    2. BRs -601,000
    3. CRs -167,658
    4. DRs -207,658
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  24. Q24Past Paper · PPSC/FPSC/NTShard

    Capital budgeting analysis 43 for warehouse automation project must correctly treat inflation in cash flows by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing consistent nominal cash flows and nominal discount rate
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 43: inflation in cash flows for warehouse automation.

  25. Q25hard

    NPV exercise 42: initial cost Rs 602,000, annual inflow Rs 97,800 for 4 years, discount rate 10%. NPV is approximately

    1. ARs -291,987
    2. BRs 310,013
    3. CRs -602,000
    4. DRs -331,987
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  26. Q26medium

    Capital budgeting analysis 41 for solar power plant project must correctly treat inflation in cash flows by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing consistent nominal cash flows and nominal discount rate
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 41: inflation in cash flows for solar power plant.

  27. Q27Past Paper · PPSC/FPSC/NTShard

    NPV exercise 40: initial cost Rs 568,000, annual inflow Rs 100,200 for 7 years, discount rate 16%. NPV is approximately

    1. ARs 404,664
    2. BRs -568,000
    3. CRs -163,336
    4. DRs -203,336
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  28. Q28medium

    Capital budgeting analysis 39 for waste treatment facility project must correctly treat sunk R&D costs treatment by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dexcluding prior R&D as irrelevant to accept-reject decision
    💡 Explanation:

    Project 39: sunk R&D costs treatment for waste treatment facility.

  29. Q29hard

    NPV exercise 38: initial cost Rs 534,000, annual inflow Rs 92,600 for 5 years, discount rate 14%. NPV is approximately

    1. ARs -216,097
    2. BRs 317,903
    3. CRs -534,000
    4. DRs -256,097
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  30. Q30Past Paper · PPSC/FPSC/NTShard

    Capital budgeting analysis 37 for ERP system project must correctly treat sunk R&D costs treatment by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dexcluding prior R&D as irrelevant to accept-reject decision
    💡 Explanation:

    Project 37: sunk R&D costs treatment for ERP system.

  31. Q31hard

    NPV exercise 36: initial cost Rs 500,000, annual inflow Rs 85,000 for 3 years, discount rate 12%. NPV is approximately

    1. ARs 204,156
    2. BRs -500,000
    3. CRs -295,844
    4. DRs -335,844
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  32. Q32Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 35 for warehouse automation project must correctly treat sunk R&D costs treatment by

    1. Aexcluding prior R&D as irrelevant to accept-reject decision
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 35: sunk R&D costs treatment for warehouse automation.

  33. Q33hard

    NPV exercise 34: initial cost Rs 501,000, annual inflow Rs 87,400 for 6 years, discount rate 10%. NPV is approximately

    1. ARs 380,650
    2. BRs -501,000
    3. CRs -120,350
    4. DRs -160,350
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  34. Q34medium

    Capital budgeting analysis 33 for solar power plant project must correctly treat sunk R&D costs treatment by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cexcluding prior R&D as irrelevant to accept-reject decision
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 33: sunk R&D costs treatment for solar power plant.

  35. Q35Past Paper · PPSC/FPSC/NTShard

    NPV exercise 32: initial cost Rs 467,000, annual inflow Rs 79,800 for 4 years, discount rate 16%. NPV is approximately

    1. ARs -243,705
    2. BRs 223,295
    3. CRs -467,000
    4. DRs -283,705
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  36. Q36hard

    Capital budgeting analysis 31 for waste treatment facility project must correctly treat opportunity cost of land by

    1. Acapitalizing all historical costs into initial outlay
    2. Bcharging foregone rent or best alternative use value
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 31: opportunity cost of land for waste treatment facility.

  37. Q37hard

    NPV exercise 30: initial cost Rs 433,000, annual inflow Rs 82,200 for 7 years, discount rate 14%. NPV is approximately

    1. ARs 352,499
    2. BRs -433,000
    3. CRs -80,501
    4. DRs -120,501
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  38. Q38Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 29 for ERP system project must correctly treat opportunity cost of land by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dcharging foregone rent or best alternative use value
    💡 Explanation:

    Project 29: opportunity cost of land for ERP system.

  39. Q39hard

    NPV exercise 28: initial cost Rs 434,000, annual inflow Rs 74,600 for 5 years, discount rate 12%. NPV is approximately

    1. ARs 268,916
    2. BRs -165,084
    3. CRs -434,000
    4. DRs -205,084
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  40. Q40medium

    Capital budgeting analysis 27 for warehouse automation project must correctly treat opportunity cost of land by

    1. Acharging foregone rent or best alternative use value
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 27: opportunity cost of land for warehouse automation.

  41. Q41Past Paper · PPSC/FPSC/NTShard

    NPV exercise 26: initial cost Rs 400,000, annual inflow Rs 67,000 for 3 years, discount rate 10%. NPV is approximately

    1. ARs 166,619
    2. BRs -233,381
    3. CRs -400,000
    4. DRs -273,381
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  42. Q42hard

    Capital budgeting analysis 25 for solar power plant project must correctly treat opportunity cost of land by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Ccharging foregone rent or best alternative use value
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 25: opportunity cost of land for solar power plant.

  43. Q43hard

    NPV exercise 24: initial cost Rs 366,000, annual inflow Rs 69,400 for 6 years, discount rate 16%. NPV is approximately

    1. ARs 255,721
    2. BRs -110,279
    3. CRs -366,000
    4. DRs -150,279
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  44. Q44Past Paper · PPSC/FPSC/NTSmedium

    Capital budgeting analysis 23 for waste treatment facility project must correctly treat depreciation tax shield by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cadding depreciation tax shield to operating cash flows
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 23: depreciation tax shield for waste treatment facility.

  45. Q45hard

    NPV exercise 22: initial cost Rs 332,000, annual inflow Rs 61,800 for 4 years, discount rate 14%. NPV is approximately

    1. ARs 180,067
    2. BRs -151,933
    3. CRs -332,000
    4. DRs -191,933
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  46. Q46medium

    Capital budgeting analysis 45 for ERP system project must correctly treat inflation in cash flows by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cusing consistent nominal cash flows and nominal discount rate
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 45: inflation in cash flows for ERP system.

  47. Q47medium

    Capital budgeting analysis 21 for ERP system project must correctly treat depreciation tax shield by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cignoring terminal year cash flows entirely
    4. Dadding depreciation tax shield to operating cash flows
    💡 Explanation:

    Project 21: depreciation tax shield for ERP system.

  48. Q48Past Paper · PPSC/FPSC/NTShard

    NPV exercise 20: initial cost Rs 333,000, annual inflow Rs 64,200 for 7 years, discount rate 12%. NPV is approximately

    1. ARs 292,993
    2. BRs -40,007
    3. CRs -333,000
    4. DRs -80,007
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  49. Q49hard

    Inflation in cash flow forecasting requires

    1. Amixing real cash flows with nominal discount rate
    2. Bignoring wage growth
    3. Cconsistent nominal or real rates and cash flows
    4. Dusing book values only
    💡 Explanation:

    Real/nominal consistency is essential.

  50. Q50Past Paper · PPSC/FPSC/NTShard

    Equivalent Annual Annuity approach helps compare projects with

    1. Aidentical cash flows only
    2. Bzero salvage always
    3. Cunequal lives
    4. Dnegative NPV only
    💡 Explanation:

    EAA converts NPV to annuity equivalent.

  51. Q51hard

    Real options in capital budgeting include

    1. Amandatory annual audit
    2. Bfixed depreciation schedule only
    3. Cstatutory tax filing
    4. Doption to expand, abandon, or delay a project
    💡 Explanation:

    Flexibility has option value.

  52. Q52Past Paper · PPSC/FPSC/NTSmedium

    Scenario analysis in capital budgeting varies

    1. Akey inputs like sales growth and cost assumptions
    2. Bonly the color of equipment
    3. Conly audit opinions
    4. Donly dividend dates
    💡 Explanation:

    Tests sensitivity to plausible scenarios.

  53. Q53medium

    Replacement decision analysis uses

    1. Aincremental cash flows of new versus old asset
    2. Bfull book value of old asset as sunk benefit
    3. Conly purchase price of new machine
    4. Dhistorical cost of both assets
    💡 Explanation:

    Compare incremental inflows and outflows.

  54. Q54Past Paper · PPSC/FPSC/NTShard

    Terminal year cash flow in NPV analysis typically includes

    1. Aonly depreciation tax shield
    2. Boperating cash flow plus after-tax salvage minus recovery adjustments
    3. Conly working capital build
    4. Donly interest expense
    💡 Explanation:

    Incremental terminal flows affect NPV.

  55. Q55medium

    Opportunity cost of using owned land for a project is

    1. Athe rent or value foregone from best alternative use
    2. Bzero because land is already owned
    3. Chistorical purchase price only
    4. Dannual depreciation only
    💡 Explanation:

    Opportunity cost is an economic concept.

  56. Q56Past Paper · PPSC/FPSC/NTSmedium

    Sunk costs in capital budgeting are

    1. Aalways subtracted from NPV
    2. Birrelevant to project accept-reject decisions
    3. Cthe primary cash flow input
    4. Dequal to opportunity costs
    💡 Explanation:

    Only incremental future cash flows matter.

  57. Q57medium

    Capital rationing exists when

    1. Afunds available for investment are limited
    2. Ball positive NPV projects can be funded
    3. CWACC is zero
    4. Ddepreciation is accelerated
    💡 Explanation:

    Firm cannot accept all value-adding projects.

  58. Q58Past Paper · PPSC/FPSC/NTShard

    Mutually exclusive projects should be ranked by

    1. AIRR always without exception
    2. BNPV when scales differ
    3. Cpayback only
    4. Daccounting profit margin
    💡 Explanation:

    IRR may conflict with NPV for mutually exclusive projects.

  59. Q59medium

    Discounted payback period improves on simple payback by

    1. Aignoring terminal salvage
    2. Busing accounting income
    3. Cdiscounting cash flows before accumulation
    4. Dexcluding initial outlay
    💡 Explanation:

    Time value incorporated in discounted payback.

  60. Q60Past Paper · PPSC/FPSC/NTSmedium

    Payback period ignores

    1. Ainitial investment amount
    2. Boperating cash inflows
    3. Cproject life entirely
    4. Dcash flows beyond the payback cutoff and time value of money
    💡 Explanation:

    Payback is a liquidity, not value, measure.

  61. Q61medium

    Profitability Index equals

    1. Apresent value of inflows divided by initial investment
    2. BNPV divided by salvage value
    3. CIRR times payback
    4. Dbook profit divided by sales
    💡 Explanation:

    PI = PV benefits / PV costs.

  62. Q62Past Paper · PPSC/FPSC/NTSeasy

    Internal Rate of Return (IRR) is the discount rate that makes

    1. Apayback period equal to project life
    2. Baccounting ROI maximum
    3. CPI equal to two
    4. DNPV equal to zero
    💡 Explanation:

    IRR solves NPV=0 for r.

  63. Q63Past Paper · PPSC/FPSC/NTSeasy

    Net Present Value (NPV) criterion accepts a standalone project when

    1. AIRR equals zero only
    2. Bpayback exceeds five years
    3. CNPV is greater than zero
    4. Daccounting profit is negative
    💡 Explanation:

    Positive NPV adds shareholder value.

  64. Q64Past Paper · PPSC/FPSC/NTShard

    NPV exercise 46: initial cost Rs 635,000, annual inflow Rs 103,000 for 3 years, discount rate 14%. NPV is approximately

    1. ARs 239,128
    2. BRs -635,000
    3. CRs -435,872
    4. DRs -395,872
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  65. Q65medium

    Capital budgeting analysis 47 for waste treatment facility project must correctly treat inflation in cash flows by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cusing consistent nominal cash flows and nominal discount rate
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 47: inflation in cash flows for waste treatment facility.

  66. Q66hard

    NPV exercise 48: initial cost Rs 669,000, annual inflow Rs 110,600 for 5 years, discount rate 16%. NPV is approximately

    1. ARs 362,137
    2. BRs -669,000
    3. CRs -346,863
    4. DRs -306,863
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  67. Q67Past Paper · PPSC/FPSC/NTShard

    Capital budgeting analysis 49 for solar power plant project must correctly treat risk-adjusted discount rate by

    1. Ausing hurdle rate reflecting project-specific business risk
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 49: risk-adjusted discount rate for solar power plant.

  68. Q68hard

    NPV exercise 50: initial cost Rs 668,000, annual inflow Rs 118,200 for 7 years, discount rate 10%. NPV is approximately

    1. ARs 575,447
    2. BRs -92,553
    3. CRs -668,000
    4. DRs -132,553
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  69. Q69medium

    Capital budgeting analysis 51 for warehouse automation project must correctly treat risk-adjusted discount rate by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing hurdle rate reflecting project-specific business risk
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 51: risk-adjusted discount rate for warehouse automation.

  70. Q70Past Paper · PPSC/FPSC/NTShard

    NPV exercise 52: initial cost Rs 702,000, annual inflow Rs 115,800 for 4 years, discount rate 12%. NPV is approximately

    1. ARs 351,725
    2. BRs -702,000
    3. CRs -390,275
    4. DRs -350,275
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  71. Q71medium

    Capital budgeting analysis 53 for ERP system project must correctly treat risk-adjusted discount rate by

    1. Ausing hurdle rate reflecting project-specific business risk
    2. Bcapitalizing all historical costs into initial outlay
    3. Cusing accounting net income without adjustment
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 53: risk-adjusted discount rate for ERP system.

  72. Q72hard

    NPV exercise 54: initial cost Rs 736,000, annual inflow Rs 123,400 for 6 years, discount rate 14%. NPV is approximately

    1. ARs 479,862
    2. BRs -736,000
    3. CRs -296,138
    4. DRs -256,138
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  73. Q73Past Paper · PPSC/FPSC/NTShard

    Capital budgeting analysis 55 for waste treatment facility project must correctly treat risk-adjusted discount rate by

    1. Acapitalizing all historical costs into initial outlay
    2. Busing accounting net income without adjustment
    3. Cusing hurdle rate reflecting project-specific business risk
    4. Dignoring terminal year cash flows entirely
    💡 Explanation:

    Project 55: risk-adjusted discount rate for waste treatment facility.

  74. Q74hard

    NPV exercise 56: initial cost Rs 770,000, annual inflow Rs 121,000 for 3 years, discount rate 16%. NPV is approximately

    1. ARs 271,753
    2. BRs -770,000
    3. CRs -498,247
    4. DRs -538,247
    💡 Explanation:

    Sum discounted inflows minus initial investment.

  75. Q75Past Paper · PPSC/FPSC/NTShard

    NPV exercise 58: initial cost Rs 769,000, annual inflow Rs 128,600 for 5 years, discount rate 10%. NPV is approximately

    1. ARs 487,495
    2. BRs -769,000
    3. CRs -321,505
    4. DRs -281,505
    💡 Explanation:

    Sum discounted inflows minus initial investment.